Permit Info
Subtype:
MAJOR ENCROACHMENT
Short Description:
Off-Site ROW work for 180 ECR
Approved Date:
10/30/2024
Expiration Date:
4/14/2026
Notes:
10/29/2024 8:35:23 AM
Address formally changed to 190 ECR
9/19/2025 8:52:12 AM
Total Inspection hours as of 9/18/25 = 230 Hours
Parcel Info
City/State/Zip:
SOUTH SAN FRANCISCO, CA, 94080
|
MISCELLANEOUS | APPROVED |
10/16/2025
| AM | 10/16/2025 | AM |
More Info
|
CONCRETE PRE-POUR | APPROVED |
9/29/2025
| AM | 9/29/2025 | AM |
More Info
|
CONCRETE | APPROVED |
9/26/2025
| AM | 9/26/2025 | AM |
More Info
|
CONCRETE PRE-POUR | APPROVED |
9/25/2025
| AM | 9/25/2025 | PM |
More Info
|
TRAFFIC CONTROL | APPROVED |
9/24/2025
| AM | 9/24/2025 | AM |
More Info
|
ASPHALT | APPROVED |
9/24/2025
| PM | 9/25/2025 | AM |
More Info
|
ASPHALT | APPROVED |
9/23/2025
| PM | 9/24/2025 | AM |
More Info
|
BACKFILL AND COMPACTION | APPROVED |
9/22/2025
| AM | 9/22/2025 | AM |
More Info
|
CONCRETE | APPROVED |
9/22/2025
| AM | 9/22/2025 | PM |
More Info
|
ASPHALT | APPROVED |
9/22/2025
| PM | 9/23/2025 | AM |
More Info
|
BACKFILL AND COMPACTION | APPROVED |
9/19/2025
| AM | 9/19/2025 | AM |
More Info
|
DEMOLITION | APPROVED |
9/18/2025
| AM | 9/18/2025 | PM |
More Info
|
CONCRETE | APPROVED |
9/17/2025
| PM | 9/18/2025 | AM |
More Info
|
COURTESY | APPROVED |
9/16/2025
| AM | 9/16/2025 | AM |
More Info
|
BACKFILL AND COMPACTION | APPROVED |
9/16/2025
| PM | 9/17/2025 | AM |
More Info
|
U/G ELECTRICAL | APPROVED |
9/15/2025
| PM | 9/16/2025 | AM |
More Info
|
U/G ELECTRICAL | APPROVED |
9/14/2025
| PM | 9/15/2025 | AM |
More Info
|
MISCELLANEOUS | APPROVED |
9/12/2025
| AM | 9/12/2025 | AM |
More Info
|
TRENCHING/EXCAVATION | APPROVED |
9/11/2025
| PM | 9/12/2025 | AM |
More Info
|
U/G ELECTRICAL | APPROVED |
9/10/2025
| PM | 9/11/2025 | AM |
More Info
|
U/G ELECTRICAL | APPROVED |
9/9/2025
| PM | 9/10/2025 | AM |
More Info
|
U/G ELECTRICAL | APPROVED |
9/8/2025
| PM | 9/9/2025 | AM |
More Info
|
POTHOLING | APPROVED |
9/7/2025
| PM | 9/8/2025 | AM |
More Info
|
MISCELLANEOUS | APPROVED |
9/4/2025
| PM | 9/4/2025 | PM |
More Info
|
U/G PLUMBING SD | APPROVED |
8/27/2025
| AM | 9/1/2025 | AM |
More Info
|
TRAFFIC CONTROL | APPROVED |
8/26/2025
| AM | 9/1/2025 | AM |
More Info
|
MISCELLANEOUS | APPROVED |
8/22/2025
| AM | 8/22/2025 | AM |
More Info
|
TRENCHING/EXCAVATION | PARTIAL |
8/19/2025
| AM | 8/19/2025 | AM |
More Info
|
DEMOLITION | APPROVED |
8/18/2025
| AM | 8/18/2025 | AM |
More Info
|
DEMOLITION | APPROVED |
8/15/2025
| AM | 8/15/2025 | AM |
More Info
|
MISCELLANEOUS | CANCELLED |
8/14/2025
| AM | 8/14/2025 | AM |
More Info
|
CONCRETE | APPROVED |
8/13/2025
| AM | 8/13/2025 | PM |
More Info
|
CONCRETE PRE-POUR | APPROVED |
8/12/2025
| AM | 8/12/2025 | PM |
More Info
|
MISCELLANEOUS | APPROVED |
8/11/2025
| AM | 8/11/2025 | PM |
More Info
|
CONCRETE | APPROVED |
8/8/2025
| AM | 8/8/2025 | PM |
More Info
|
CONCRETE PRE-POUR | APPROVED |
8/7/2025
| AM | 8/7/2025 | PM |
More Info
|
MISCELLANEOUS | APPROVED |
8/6/2025
| AM | 8/6/2025 | PM |
More Info
|
MISCELLANEOUS | APPROVED |
8/4/2025
| AM | 8/4/2025 | AM |
More Info
|
TRAFFIC CONTROL | APPROVED |
7/29/2025
| AM | 7/29/2025 | AM |
More Info
|
DEMOLITION | APPROVED |
7/28/2025
| AM | 7/28/2025 | PM |
More Info
|
BACKFILL AND COMPACTION | APPROVED |
7/25/2025
| AM | 7/25/2025 | PM |
More Info
|
BACKFILL AND COMPACTION | APPROVED |
7/24/2025
| AM | 7/24/2025 | PM |
More Info
|
SUBGRADE | APPROVED |
7/23/2025
| AM | 7/23/2025 | PM |
More Info
|
DEMOLITION | APPROVED |
7/22/2025
| AM | 7/22/2025 | PM |
More Info
|
DEMOLITION | APPROVED |
7/21/2025
| AM | 7/21/2025 | PM |
More Info
|
PRE-POUR ASPHALT/CONCRETE | APPROVED |
7/7/2025
| AM | 7/7/2025 | AM |
More Info
|
PRE-CONSTRUCTION MEETING | APPROVED |
7/1/2025
| AM | 7/1/2025 | AM |
More Info
|
SITE CLEANUP | APPROVED |
6/25/2025
| AM | 6/25/2025 | AM |
More Info
|
U/G ELECTRICAL | APPROVED |
6/23/2025
| AM | 6/23/2025 | AM |
More Info
|
DEMOLITION | APPROVED |
6/18/2025
| PM | 6/18/2025 | PM |
More Info
|
MISCELLANEOUS | APPROVED |
6/17/2025
| PM | 6/17/2025 | PM |
More Info
|
U/G PLUMBING SD | APPROVED |
5/27/2025
| AM | 5/27/2025 | AM |
More Info
|
ASPHALT | APPROVED |
5/22/2025
| AM | 5/22/2025 | PM |
More Info
|
MISCELLANEOUS | APPROVED |
5/22/2025
| PM | 5/22/2025 | PM |
More Info
|
ASPHALT | APPROVED |
5/21/2025
| AM | 5/21/2025 | PM |
More Info
|
CONCRETE | APPROVED |
5/21/2025
| PM | 5/21/2025 | PM |
More Info
|
ASPHALT | APPROVED |
5/20/2025
| AM | 5/20/2025 | PM |
More Info
|
BACKFILL AND COMPACTION | APPROVED |
5/20/2025
| PM | 5/20/2025 | PM |
More Info
|
ASPHALT | APPROVED |
5/19/2025
| AM | 5/19/2025 | PM |
More Info
|
BACKFILL AND COMPACTION | APPROVED |
5/19/2025
| PM | 5/23/2025 | PM |
More Info
|
ASPHALT | APPROVED |
5/16/2025
| AM | 5/16/2025 | PM |
More Info
|
ASPHALT | APPROVED |
5/16/2025
| PM | 5/16/2025 | PM |
More Info
|
ASPHALT | APPROVED |
5/15/2025
| AM | 5/15/2025 | PM |
More Info
|
ASPHALT | APPROVED |
5/15/2025
| PM | 5/15/2025 | PM |
More Info
|
MISCELLANEOUS | CANCELLED |
5/14/2025
| AM | 5/14/2025 | AM |
More Info
|
U/G ELECTRICAL | APPROVED |
5/13/2025
| AM | 5/13/2025 | PM |
More Info
|
U/G ELECTRICAL | APPROVED |
5/13/2025
| PM | 5/13/2025 | PM |
More Info
|
MISCELLANEOUS | CANCELLED |
5/12/2025
| AM | 5/12/2025 | AM |
More Info
|
ASPHALT | APPROVED |
5/8/2025
| AM | 5/8/2025 | |
More Info
|
ASPHALT | APPROVED |
5/6/2025
| AM | 5/6/2025 | |
More Info
|
SD CATCH BASIN | APPROVED |
5/6/2025
| AM | 5/6/2025 | |
More Info
|
CONCRETE | APPROVED |
5/5/2025
| AM | 5/6/2025 | |
More Info
|
JOINT TRENCH | APPROVED |
5/5/2025
| PM | 5/6/2025 | |
More Info
|
JOINT TRENCH | APPROVED |
5/2/2025
| AM | 5/6/2025 | |
More Info
|
JOINT TRENCH | APPROVED |
5/1/2025
| AM | 5/6/2025 | |
More Info
|
JOINT TRENCH | APPROVED |
4/30/2025
| AM | 5/6/2025 | |
More Info
|
JOINT TRENCH | APPROVED |
4/29/2025
| AM | 4/29/2025 | |
More Info
|
JOINT TRENCH | APPROVED |
4/28/2025
| AM | 4/29/2025 | |
More Info
|
JOINT TRENCH | |
4/25/2025
| | | |
More Info
|
JOINT TRENCH | |
4/24/2025
| | | |
More Info
|
JOINT TRENCH | APPROVED |
4/23/2025
| AM | 5/6/2025 | |
More Info
|
JOINT TRENCH | APPROVED |
4/22/2025
| AM | 5/6/2025 | |
More Info
|
U/G HYDRO | APPROVED |
4/22/2025
| AM | 5/6/2025 | |
More Info
|
JOINT TRENCH | APPROVED |
4/18/2025
| AM | 5/6/2025 | |
More Info
|
U/G HYDRO | APPROVED |
4/17/2025
| AM | 5/6/2025 | |
More Info
|
JOINT TRENCH | |
4/16/2025
| | | |
More Info
|
ASPHALT | |
2/28/2025
| | | |
More Info
|
ASPHALT | APPROVED |
2/24/2025
| AM | 3/2/2025 | |
More Info
|
ASPHALT | APPROVED |
2/21/2025
| AM | 3/2/2025 | |
More Info
|
U/G PLUMBING SD | APPROVED |
2/21/2025
| AM | 3/2/2025 | |
More Info
|
CONCRETE | APPROVED |
2/20/2025
| AM | 3/2/2025 | |
More Info
|
CONCRETE PRE-POUR | APPROVED |
2/20/2025
| AM | 3/2/2025 | |
More Info
|
TRENCHING/EXCAVATION | APPROVED |
2/7/2025
| AM | 2/7/2025 | |
More Info
|
U/G ELECTRICAL | APPROVED |
2/5/2025
| AM | 2/7/2025 | |
More Info
|
U/G ELECTRICAL | APPROVED |
1/31/2025
| AM | 2/7/2025 | |
More Info
|
U/G ELECTRICAL | APPROVED |
1/30/2025
| AM | 2/7/2025 | |
More Info
|
U/G PLUMBING SD | APPROVED |
1/30/2025
| AM | 2/7/2025 | |
More Info
|
PRE-CONSTRUCTION MEETING | APPROVED |
1/15/2025
| AM | 1/15/2025 | |
More Info
|
POTHOLING | APPROVED |
12/19/2024
| AM | 12/19/2024 | |
More Info
|
POTHOLING | APPROVED |
12/18/2024
| AM | 12/19/2024 | |
More Info
|
U/G PLUMBING SD | APPROVED |
12/11/2024
| AM | 12/12/2024 | |
More Info
|
U/G PLUMBING SD | APPROVED |
12/10/2024
| AM | 12/12/2024 | |
More Info
|
There are currently no reviews on this record.